What must a municipality's Official Plan receive before full implementation?

  1. Approval from the federal government.

  2. Review by the Local Planning Appeal Support Centre.

  3. Community feedback.

  4. Final approval from the provincial government.

  5. Verification by the Municipal Affairs Committee.

  6. Endorsement from the local real estate board.

The correct answer is: Final approval from the provincial government.

In Ontario, a municipality's Official Plan must receive final approval from the provincial government before full implementation. This is because the Planning Act in Ontario mandates that Official Plans must align with provincial interests and policies. Therefore, the correct answer is D. Options A, B, C, E, and F are incorrect as they do not have the authority to grant final approval for the implementation of the Official Plan in a municipality in Ontario.